Floor repairs in the Joy Burns Arena and Coors Fitness Center continue through this week. Joy Burns Arena flooring is expected to be in place by today Wednesday, August 26, including in the Joy Burns Arena locker rooms. Crews continue to finish painting with FRP scheduled in one locker room at a time, for roughly two days maintenance on each locker room. Locker rooms are expected to be completed by the end of next week.

Coors Fitness Center members continue to access the Crimson Locker Rooms through the pool entrance on the west concourse. Flooring maintenance is on schedule and expected to be completed by end of day Friday, August 28. We expect to gain access to the Gold Club Locker Rooms and first floor Coors Fitness Center lobby on Saturday, August 29 with flooring will still being done in the lobby in different installments so that we will still have access to the space.

We continue to thank you for your patience during this time as we are near flood repair completion for Joy Burns Arena and Coors Fitness Center locker rooms!